This weekend we didn’t bother driving up to the house, since we could not get inside anyway – the final coat of polyurethane on the hardwood floors is drying. Otherwise, we would have tried to get the last couple of loads of boxes out of the storage unit – and it might have been just as well that we couldn’t, since I have a miserable, standard-issue head cold and spent large blocks of time in the recliner napping!
The painters AGAIN took an unannounced week off, but have said they will be back to work on Monday, 2/4. However, my list from two weeks ago has shrunk:
INSIDE:
Interior painting: Done except for minor touch-ups
Install light fixtures
Install kitchen backsplash
Install kitchen appliances
OUTSIDE:
Install porch railings: this week??
Install gutter, downspouts
Exterior painting: To begin 2/4?
Pour concrete: Garage floor done, driveway still to do
Install garage doors
Grade, seed, hay yard: After the mud dries………
What is that expression about watching paint dry?